1 Construction of 50,000 Gallon Over Head Reservoir at Muhallah Rung Pura Sialkot 2.70 1969-1970
2 Construction of 50,000 Gallon Overhead Reservoir at Nankana Sahib 4.00 1972-1973
3 Providing & Laying 45” i/d Pressure Type Sewerage under 13” depth water 6.00 1974
4 Construction of 30,000 Gallon Overhead Reservoir at Railway Station of Kot Radha Kishan 6.00 1976
5 Re-construction of Shrine Hazrat-Madhu-Laal-Hussain Lahore  10.66 2014-2016

Housing & Physical Department

Sr. # Project Cost Year
1 Construction of 50,000 Gallon Overhead Reservoir and sewerage scheme at low income Housing scheme no.2 Wasan Pura Lahore 8.00  1975-1976
2 Construction of 50,000 Gallon Over Head Reservoir and sewerage scheme in low income Housing scheme at Nankana Sahib 5.00  1976-1977
3 Sewerage scheme at Nankana Sahib 5.80  1977

Auqaf & Religious Affairs Department

Sr. # Project Cost Year
1 Construction of 50,000 Gallon Overhead Reservoir at Data Darbar, Lahore 1.70 1979
2 Construction of Medical ward and shops at Data Darbar Hospital 0.50 1982
3 Construction of 2 Nos. Quarters at Shah Kamal Colony 0.50 1985
4 Construction of Boundary Wall and Langar Khana at Shrine of Imam Ali-ul-Haq Sialkot 0.50 1985
5 Construction of Maternity Outdoor Ward at Data Darbar Hospital 1.40  1984-1985
6 Construction of Operation Theater of Gynae Ward and General Ward at Data Darbar Hospital 1.40  1986-1987
7 Construction of Development Scheme Hzt. Baba Farid-ud-Din and 30,000 Gallon overhead Reservoir at Shrine 8.00  1989-1990
8 Construction of Lawyer Chamber near High Court, Lahore 2.60  1989-1990
9 Construction of shops Zaireen Complex 10.00 1990
10 Extension of Jamia Masjid Auqaf Colony Shah Kamal 1.30 1993
11 Construction of Zaireen complex at Bibi Pak Daman, Lahore 5.50 1995
12 Construction of Model Mosque at shrine of Hzt. Sakhi Saiden Shah Sherazi, Choa Saiden Shah Chakwal 7.20 1996
13 Construction of Model Mosque at shrine of Hazrat Baba Bulleh Shah, Kasur 15.70  2000
14 Construction of shops, offices and shrine of Sain Allah Rakha, Faisalabad 8.70  2001
15 Re-Construction of Hazrat Baba Bulleh Shah shrine, Kasur 14.30  2002
16 Construction of Flats at shopping center attached to Jamia Masjid Markazi Rawalpindi 17.65  2006
17 Construction of shopping Center at Waqf Allah Rakha Trust, Delhi Gate Lahore 11.60  2007
18 Construction of Madrassa Dar-ul-Uloom at Waqf Plot, Muslim Town Bahawalpur 11.78  2007
19 Construction of Madrassa and Mosque Anwar-e-Madina at Ferozpur Road Kahna Nau Lahore 27.69  2007
20 RCC Retaining wall at shrine of Hzt. Baba Farid, Pak Pattan 5.75  2007
21 Construction of Development scheme at shrine of Hazrat Madhu Laal Hussain, Lahore  34.33 2010
22 P/L Sewer pipe line & Improvement of roads at Data Darbar Hospital, Lahore  41.70  2012
23 Construction of RCC Wall at shrine of Kamal Chishtian, Kasur   20.20  2015
24 Re-Construction of Shrine Hazrat Madhu Laal Hussain, Lahore 10.66  2016
25 Extension/up-gradation of the shrine of Hazrat khawaja Ghulam Fareed (R.A) Kot mithan, District Rajan Pur  73.00  2022-2023

University of Engineering & Technology Lahore

Sr. # Project Cost Year
1 Construction of Mathematics Department 2.45 1995
2 Construction of Geological Engineering Labs and Library in the Department of Mining & Geological Engineering 13.70 2002
3 Construction of Al-Zohra girls Hostel 5.00 2004
4 Extension of Civil Engineering Department 11.90 2004

University of Engineering & Technology Kala Shah Kaku Campus

Sr. # Project Cost Year
1 Construction of Mechanical Engineering Department 65.00 2006
2 Construction of Electrical Engineering Department 40.00 2006
3 Construction of 16000 Rft Boundary Wall of UET KSK Campus 10.00 2006
4 Construction of Main Entrance Gate of UET KSK Campus 3.40 2007
5 Construction of Chemical Engineering Department 70.00 2007
6 Construction of 65000 Gallon Overhead Water Reservoir 13.50 2009
7 Construction of Mosque at Faisalabad Campus 34.60 2015

Anjuman Himayet-I-Islam

Sr. # Project Cost Year
1 Construction of D-Plaza at Multan Road, Lahore 73.20 2006
2 Construction of Charity Plaza at Multan Road, Lahore 180.00 2006

Daanish Schools and Centers of Excellence Authority

Sr. # Project Cost Year
1 Upgradation of Daanish School at Chishtian Distt Bahawalnagar. Group No. 1-A (Boys Campus) Buildings & Roads 210.281  2016-19
2 Upgradation of Daanish School at Chishtian Distt Bahawalnagar. Group No. 1-B Auditorium 63.456  2016-19
3 Upgradation of Daanish School at Chishtian Distt Bahawalnagar. Group No. 2 (Girls Campus) Buildings & Roads 210.984  2016-19

DESCOS & NTDC

Sr. # Project Cost Year
1  Lot-1 : Procurement of Plant, Design, Supply, Installation, Testing and Commissioning of Conversion Work from 66kV to 132kV on Turn Key basis at KOT SULTAN (Main Contractor: PEL & Subcontractor: CMA) 45.00  2019-2020
2  Procurement of Plant- Design, Manufacture, Supply, Installation, Testing & Commissioning of 500kV Double Circuit Quad Bundle Transmission Line from Suki Kinari Hydro Power Station to Interconnection Point of Existing Neelum Jhelum 500kV Double Circuit Quad Bundle Transmission Line (approx. 75km), using ACSR “Bunting” Conductor.
SUBCONTRACTING AGREEMENT OF ACCESS ROADS FOR: (Main Contractor: CEEC NEPC-II & Subcontractor: CMA)
323.00  2019-2020